LogicPLUS-S Two-Wire Controller
18
18
Position 6 | | Calendar | | Function Button Odd-Even
: May be accessed by pressing Function Key Set 5.
This is the day of the calendar that the program will start. This will be automatically set upon
initial programming or set by the user. This is day 1 of the calendar, the day you set up the calendar
or programmed the program or let the auto-calendar set up the calendar.
The total run time of the program has carried over into the second or more days and the
program will be running these days to complete.
The user has programmed in additional days that the program will not be active.
For calculating the calendar for “Run” Times over 24 hours. This example is for 56 hours Run Time
per Program.
If a start time is 8:00 am, then the rst calculation would be 8 hours plus a total run time
of 56 hours for a grand total of 64 hours, divided by 24 hours would equal a 2.67 day calendar, the
display would show a 3 day calendar, as follows, day 1 STRT, day 2 RUN and day 3 RUN. If you
wanted to irrigate every 4th day, use set 2 to expand the calendar from 3 days to 4 days, day 4
would show OFF.